Oxygen station ASU-24K launched

Our service engineers put into operation a modular oxygen plant
Order a project
131
Our service engineers commissioned a modular oxygen plant with a capacity of 96 oxygen bottles per day. Thanks to the modular design, the start-up, installation and commissioning of the station took 4 days, 2 of which the station worked on filling the cylinders. All parameters of the station correspond to the passport values, the oxygen quality corresponds to 95%. The plant automation system allows one operator to operate the station without constant presence, when the cylinders are filled up to 150 bar, the station automatically goes into standby mode.
All news
Submit your inquiry
If you are interested in our equipment and you want to receive detailed information